Change Order #3F to RCS Construction for Northridge Water Booster Station, Project No. W10-1898 / CIP No. 50834, for an increase of $7,581.73 |
|||
Summary: |
|||
An increase to the construction contract based on actual quantities installed. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
0934 Water |
|||
Recommendation: |
|||
Action: Approve Notes: |
|||